Additional Capacity Expansion Of 600,000 Tonnes Coke

BackJul 09, 2008

 The construction of additional capacity expansion facility of  600,000 tonnes metallurgical coke has been completed in May 2008. The cost of construction was RMB 370 million. Since 1 June 2008, the new facility has been successfully commissioned. The utilization rate of the new facility for June 2008 was approximately 70%.We expect the utilization rate for July & August  2008 to be approximately 80% &  90% respectively. Thereafter, we expect the utilization rate to hit 100% capacity, thus resulting in our total production capacity per annum to reach 1.8 million tonnes.